Three interconnections to rising mains, to provide three additional supply lines to Chinchilla's service connections, to allow work to be performed to the water tower discharge location, without a water disruption to Chinchilla.
Supply and installation of approx 65m of 355mm PE pipe and connection to various existing services.
Challenges associated with this job was to reduce the amount of disturbance to the town water supply and minimise the impact to local business and the community.
Construction of a new principal depot for Toowoomba regional council simultaneous delivery of multiple buildings across a 28Ha Greenfield site including a Central operations building, 3 workshops, a
Commenced in December 2016 this project required the relocation of over 9km of water and gas infrastructure through the town of Dalby, to accommodate the widening and major upgrade of the Warrego
The Glen McCracken Gymnasium at Toowoomba Grammar School is equivalent in height to a 6 Storey Apartment Block, the upper level house 2 Full Sized basketball courts as well as a Canteen and amenities